167 mheight
50floors
2022completed
592homes
13permits

Development milestones

Planning application2015Planning application TPM-2015-37 lodged
ApprovedBy 2019Planning permit granted (exact date not recorded)
Construction startedDec 2019First major construction permit issued
First occupantsJun 2022First occupancy permit issued
CompletedBy Dec 2022Focus Melbourne Apartments completed: 50 floors

Building team

Developer
Central Equity
Developer
WKB Land Corporation
Architect
Doig Architecture
Builder
Multiplex

Planning & subdivision

Zone
CCZ3
Overlays
DDO1, DDO10, DDO27, LSIO4, PO1
Strata plan
PS819871 · 1,107 lots
Scores
🚆 8 · ☕ 9 · 🌳 10 · ✨ 8

Timeline

20251 building permit · about $50k of new works
Largest: Internal Fit-Out (Tenancy 3) - Mr Summit
14 Dec 2023Focus Melbourne wins UDIA Victoria Apartments (High-Rise) Award
The UDIA Victoria awards listed Focus Melbourne by Central Equity as a winner of the Apartments (High-Rise) Award. The entry describes a 50-level tower with 591 apartments and a ground-floor commercial space.
23 Nov 2023Focus Melbourne wins Victorian HIA housing award
Focus Melbourne won the Victoria Apartment Complex Award (over $20 million) at the 2023 HIA-CSR Victorian Housing Awards. The article credited Central Equity as developer and Doig Architecture as designer.
2023Council census records it as residential apartment, 50 floors
20239 certificates · about $2.7m of new works
Largest: Stage 13 - Podium Architectural Works
1 Dec 2022Multiplex reaches practical completion on Focus
In December 2022, Multiplex announced practical completion of the $450 million Focus tower, described as 50 storeys with 591 apartments and a six-level commercial podium. A later Southbank Local News article said the building was complete and ready to move in.
By Dec 2022Focus Melbourne Apartments completed: 50 floors
Derived from Property Markets News
Jun 2022First occupancy permit issued
Derived from City of Melbourne building permits
20221 building permit and 10 certificates · about $130k of new works
Largest: Stage 14 - Building Facade Level 7 to 39
2021Council census records it as unoccupied - under construction, 3 floors
20213 building permits
Largest: Stage 18 - Architectural Fitout - Level Lift Pit to Level 6 and Ground Floor Civil Works
1 May 2020Construction commences on Focus
An article dated May 2020 reported that construction had commenced on Focus, described as 592 apartments across 50 levels at 75 City Road. It did not give a start date.
2020Council census records it as unoccupied - under demolition/condemned, 1 floors
20202 building permits · about $238.9m of new works
Largest: Stage 5 - Vertical Structural Elements Ground to Level 6
By 2019Planning permit granted (exact date not recorded)
Derived from City of Melbourne Development Activity Monitor
Dec 2019First major construction permit issued
Derived from City of Melbourne building permits
2019Council census records it as unoccupied - unused, 3 floors
20191 building permit · about $1.2m of new works
Largest: Demolition of building excluding heritage facade to 71-75 City Road conditional
20181 building permit · about $10k of new works
Largest: Stage 1 - Repair of Existing Facade
2017Council census records it as unoccupied - unused, 3 floors
Name recorded: Southbank Terrace
2015Planning application TPM-2015-37 lodged
Derived from City of Melbourne Development Activity Monitor
6 Oct 2015Original 67-level, 224.6 m tower proposed for 71-87 City Road
A 2015 article described a proposed 67-level residential tower at 71-87 City Road, designed by Doig Architecture, at 224.6 metres with 782 apartments.
2015Council census records it as office, 3 floors
Name recorded: Southbank Terrace
2013Council census records it as unoccupied - unused, 3 floors
Name recorded: SOUTHBANK TERRACE
20051 certificate · about $40k of new works
Largest: Alteration to office
2004Council census records it as office, 3 floors
Name recorded: SOUTHBANK TERRACE
2002First council census entry: unoccupied - unused, 3 floors
20001 building permit · about $106k of new works
Largest: office alts
19991 building permit · about $175k of new works
Largest: Office fitout
19981 building permit and 1 certificate · about $105k of new works
Largest: Remove partitions in offices on ground, first and second floors
19971 building permit · about $45k of new works
Largest: Office partition alterations

Building permits and certificates (34)

Each cost is the estimate on that record. Stages of a project often repeat its full value, so these don't add up to what was spent.

02 Dec 2025Internal Fit-Out (Tenancy 3) - Mr Summit$50k
08 Nov 2023M01, 101, 201, 401, 501 & 601. Proposed alterations to existing office tenancies.$12k
16 Aug 2023Tenancy Fitout (Tenancies 2, 10-12 and 4-9)$2.7m
02 June 2023Stage 13 - Podium Architectural Works$238.9m
02 June 2023Stage 17 - Architectural Fitout - Level 7 to Roof$238.9m
02 June 2023Stage 2 - Piling to West Corner of Site between Gridlines 1 and 6 - Conditional$217.2m
02 June 2023Stage 4 - In-Ground Services, Slab on Ground$217.2m
01 June 2023Stage 16 - Architectural Basebuild - Level 7 to Roof$238.9m
01 June 2023Stage 22 - Building facade (podium balustrades , canopies and pool roof)$0
01 June 2023Stage 7 - Variation Core Levels 5,6,7$0
14 Oct 2022Stage 14 - Building Facade Level 7 to 39$238.9m
14 Oct 2022Stage 20 - Steelwork and Miscellaneous Structure (Tower); and Crash Barriers (Podium)$238.9m
14 Oct 2022Stage 6 - PT Slabs Mezzanine to Level 6$217.2m
12 Oct 2022Stage 2A - Variation - Piles to Gridlines 6-8 - Conditional$217.2m
12 Oct 2022Stage 9 - Services lift pit to level 6, soffit insulation and substation fitout works.$217.2m
05 Sept 2022Stage 11 - PT slabs levels 7 to 48$238.9m
05 Sept 2022Stage 15 - Services - Level 7 to Roof$238.9m
05 Sept 2022Stage 21 - Level 40 to 50 Building Facade.$238.9m
28 Aug 2022Tenancy 1, Ground floor - Alteration$130k
17 June 2022Stage 19 - PT Slabs Level 48 - Roof$238.9m
17 June 2022Stage 8 - Verticals level 6 to roof.$217.2m
23 Aug 2021Stage 18 - Architectural Fitout - Level Lift Pit to Level 6 and Ground Floor Civil Works$238.9m
19 Mar 2021Stage 12 - Podium Facade up to Level 7$238.9m
04 Mar 2021Stage 10 - Structural steel and miscellaneous structure podium$217.2m
28 May 2020Stage 5 - Vertical Structural Elements Ground to Level 6$217.2m
02 Apr 2020Stage 3 - Pile Capping Beam, Excavation and In-ground Structure$217.2m
03 Dec 2019Demolition of building excluding heritage facade to 71-75 City Road conditional$1.2m
05 Sept 2018Stage 1 - Repair of Existing Facade$10k
21 Mar 2005Alteration to office$40k
01 Dec 2000office alts$106k
10 Dec 1999Office fitout$175k
22 June 1998Alterations to toilets on level 1$5k
18 June 1998Remove partitions in offices on ground, first and second floors$100k
15 Sept 1997Office partition alterations$45k

Questions and answers

Is Focus Melbourne Apartments residential or commercial?
Focus Melbourne Apartments mixes homes and businesses under one roof. The City of Melbourne lists its main use as residential apartment.

When was Focus Melbourne Apartments built?
Focus Melbourne Apartments was completed in 2022.

How many floors does Focus Melbourne Apartments have?
Focus Melbourne Apartments has 50 floors above ground.

How many apartments are in Focus Melbourne Apartments?
Focus Melbourne Apartments has 592 homes. The national address file lists 830 unit addresses here, and some of those can be shops or offices.

What size apartments are in Focus Melbourne Apartments?
The City of Melbourne's development record lists 252 1 bed, 208 2 bed and 132 3+ bed apartments. The built numbers may differ a little.

Does Focus Melbourne Apartments have parking?
The City of Melbourne records 284 residential car spaces at this property. Which apartments have a space isn't recorded, so check the listing.

What do apartments cost near Focus Melbourne Apartments?
The median unit price in Southbank was $580,000 in 2025, from the Victorian Property Sales Report. That's for the whole suburb, not this building.

What businesses are in Focus Melbourne Apartments?
The latest council census counted 1 business in Focus Melbourne Apartments, including FOCUS MELBOURNE APARTMENTS PTY LTD.

Are there apartments for sale or rent in Focus Melbourne Apartments?
See the residential listings on this page, or use the shortcuts to search 71-87 City Road on realestate.com.au and Domain.

Is there office or retail space for lease in Focus Melbourne Apartments?
See the commercial listings on this page, or search this address on realcommercial.com.au and commercialrealestate.com.au.

Who designed and built Focus Melbourne Apartments?
WKB Land Corporation developed Focus Melbourne Apartments, Doig Architecture designed it and Multiplex built it. The building team section has the sources.

How tall is Focus Melbourne Apartments?
About 166 metres, measured from the City of Melbourne's 3D building model. It's number 11 of 190 buildings in Southbank by height.

What public transport is near Focus Melbourne Apartments?
Flinders Street Station is the nearest train station, about 5 minutes' walk. The nearest tram stop is Arts Precinct/Sturt St #17, about 3 minutes' walk.

What is the planning zone for Focus Melbourne Apartments?
The site is in the Capital City Zone - Schedule 3 (CCZ3).

Does Focus Melbourne Apartments have an owners corporation?
Plan of subdivision PS819871 has 1,107 lots and common property, which means it is managed by an owners corporation.

Was a taller tower proposed for the site?
Yes. In 2015 a 67-level, 224.6 metre tower was proposed for 71-87 City Road. The finished building has 50 floors and stands 167 metres.

What awards has Focus Melbourne Apartments won?
It won the UDIA Victoria Apartments (High-Rise) Award in December 2023 and a Victorian HIA housing award in November 2023.

Has any work been done on Focus Melbourne Apartments recently?
The City of Melbourne has issued 13 building permits for Focus Melbourne Apartments since 1997. The most recent was in December 2025.

Sources: City of Melbourne building permits (CC BY 4.0); CLUE building information (CC BY 4.0); CLUE business establishments (CC BY 4.0); CLUE residential dwellings (CC BY 4.0); Development Activity Monitor (CC BY 4.0); Geocoded National Address File (G-NAF) (Open G-NAF EULA (CC BY 4.0 based)). General information from public records, not legal, financial or building advice.

Suggest a correction

Something wrong or missing? Tell us what it should say. We check every suggestion before changing anything.

By sending, you agree to the contributor terms. See how we handle your details in the privacy policy.