| Planning application | 2019 | Planning application TPMR-2019-9/A lodged |
| Approved | By 2019 | Planning permit granted (exact date not recorded) |
| Construction started | May 2019 | First major construction permit issued |
| First occupants | May 2023 | First occupancy permit issued |
| Completed | 2023 | Enterprise House - 555 Collins Street completed: 35 floors |
Each cost is the estimate on that record. Stages of a project often repeat its full value, so these don't add up to what was spent.
| 30 Apr 2026 | Levels 31 & 32 - Fit-out of Offices | $231k |
| 20 Apr 2026 | Level 21 - Tenancy Fitout | $50k |
| 19 Mar 2026 | Fit-out of Offices - Levels 31 & 32 | $2.8m |
| 16 Jan 2026 | Office fitout for HFW – Level 33 & Level 34 - Stage 1: Fit-out works excluding intertenancy stair & barriers. | $5.8m |
| 01 Dec 2025 | Alterations to existing building - fitout works to Level 5 | $4.5m |
| 01 Dec 2025 | AWS Fit Out on Levels 6 & 7, 555 Collins Street, Melbourne - stage 1: site establishment works | $61.1m |
| 31 Oct 2025 | The proposed project is for the IT Wall & Slab Infill located at Level 33, 555 Collins Street Melbourne. | $805k |
| 27 Aug 2025 | Levels 6, 8 - 11 & 20 - Installation of New Amazon Phone Booths to Existing Offices | $258k |
| 28 July 2025 | Alterations to existing building - security upgrade works | $565k |
| 06 June 2025 | Ground floor restaurant fitout | $2.5m |
| 23 May 2025 | Level 2, 3 & 4 Only - Proposed Internal Office Fitout for Bendigo Bank | $132.0m |
| 23 May 2025 | Stage 2 - To permit structural cut-out for stair void between level 2 and 3 only. | $13.2m |
| 23 May 2025 | Stage 4 - To permit remainder of proposed works | $12.0m |
| 23 Apr 2025 | Level 30 - Office fitout to existing tenancy | $983k |
| 06 Mar 2025 | Alterations to existing building - Amazon tenancy works | $260k |
| 24 Feb 2025 | Stage 2 - All remaining works to completion | $2.5m |
| 10 Feb 2025 | Stage 3 - To permit remainder of proposed fitout works excluding sunken lounge and phone booths | $12.0m |
| 09 Dec 2024 | Ground Level Food & Beverage Tenancy Split - Stage 2 - Under slung works and services provision for cool room | $1000k |
| 06 Dec 2024 | Project is for the Office Alterations within Level 6 at 555 Collins Street, Melbourne. | $277k |
| 16 Oct 2024 | Ground Level Food & Beverage Tenancy Split - Stage 1 - Intertenancy wall and services relocation | $612k |
| 11 June 2024 | Stage 1 - Level 1, 6 -13. Construction of an alteration of a building | $41.5m |
| 11 June 2024 | Stage 2 - Remaining tenancy fitout works Level 1, 8 to 13 | $1.0m |
| 11 June 2024 | Stage 3 - Alterations to the terrace on level 10 | $200k |
| 19 Apr 2024 | Stage 2 - Level 13 - Alterations to terrace on level 10 and level 13 north and east terraces | $866k |
| 12 Mar 2024 | Level 30, 555 Collins St - Spec Suite Alterations - Tenancy Split and Fit out works. | $2.1m |
| 29 Feb 2024 | Tenancy 1 - Level 21 - Office Fitout | $1.9m |
| 15 Feb 2024 | Level 29 -Connective Office Fitout | $3.9m |
| 05 Feb 2024 | Levels 24-28. Office fitout to existing tenancy, including new inter-connecting stair. | $22.4m |
| 09 Jan 2024 | Level 13 - Alterations to west side terrace. | $866k |
| 09 Jan 2024 | Stage 2 - Level 13 - Alterations to terrace on level 10 and level 13 north and east terraces | $866k |
| 15 Nov 2023 | Stage 3 - Installation of Sky Signage | $500k |
| 31 Oct 2023 | Stage 1: All internal fit out work from Level 14 to Level 19 excluding: · Installation of the fire curtain | $19.0m |
| 31 Oct 2023 | Stage 2: Level 14 to 19 - tenancy fit out - Balance of Works (Installation of fire curtain) | $19.0m |
| 31 Oct 2023 | Stage 39 - Lower Ground Staff Amenities | $312.0m |
| 23 Oct 2023 | Stage 37: Construction of Bridge Link between 555 Collins Street Melbourne to 567 Collins Street Melbourne. Excluding Fire & hydraulic services discharge to link bridge. | $312.0m |
| 16 Oct 2023 | Ground Floor, 555 - Barista Bar at Enterprise House | $209k |
| 27 Sept 2023 | Stage 1: Wellness Centre Fit Out - Architectural & Services Fit Out, excluding Hearing augmentation system & lighting design | $3.1m |
| 27 Sept 2023 | Stage 2: Lower Ground Hearing Augmentation and Lighting Services | $3.2m |
| 27 Sept 2023 | Stage 3: Architectural & Services Fit out to Levels 6 & 20, Excluding Electrical & Lighting Installation. | $18.1m |
| 27 Sept 2023 | Stage 4: Electrical Services to Levels 1, 2, 6 & 20. | $18.1m |
| 20 Sept 2023 | Stage 2 - Level 29 555 Collins - Architectural and Services. Balance of works. | $3.9m |
| 20 Sept 2023 | Stage 5: Multiple Levels of Fitout (Separate Tenancies) at Levels 1, 2, 6 & 20 - Level 1 and 2 Interconnecting Stair | $18.1m |
| 19 Sept 2023 | Stage 40 - Fire & hydraulic services discharge to link bridge. | $312.0m |
| 13 Sept 2023 | Stage 6: Level 1 Hearing Augmentation System | $18.1m |
| 11 Sept 2023 | Installation of Feature Artwork Ceiling | $276k |
| 08 Sept 2023 | Level 4 tenancy void | $950k |
| 25 Aug 2023 | Alteration to an existing building - Internal office fitout | $7.2m |
| 22 Aug 2023 | Level 11 - Internal Office Fitout for Lombardi Partners | $132k |
| 20 July 2023 | Stage 38 - Level 21 Intertenancy Partition Wall | $312.0m |
| 14 July 2023 | Levels 24-28. Office fitout to existing tenancy, including new inter-connecting stair. | $22.4m |
| 30 June 2023 | Stage 1: Wellness Centre Fit Out - Architectural & Services Fit Out, excluding Hearing augmentation system & lighting design | $3.1m |
| 20 June 2023 | Stage 3 - Installation of Sky Signage | $500k |
| 19 June 2023 | Stage 2 : Level 1 Architectural and Services work excluding Interconnecting Stair, Artificial Lighting, Hearing Augmentation and J6 Report. | $18.1m |
| 05 June 2023 | Stage 1: Level 2 Architectural and Services (Only) Excluding the following works, - Phonebooths, - Interconnecting Stair, - Artificial Lighting - Part J6 Report. | $18.1m |
| 15 May 2023 | Stage 10 - Level 1 Suspended Slab | $275.0m |
| 15 May 2023 | Stage 11 - Level 2 Suspended Slab | $275.0m |
| 15 May 2023 | Stage 12 - Level 3 Suspended Slab, Blockwork Walls from Basement 2 to the Underside of Ground Floor, Secondary Slab to Basement 2 | $275.0m |
| 15 May 2023 | Stage 13 - Level 4 to Level 6 suspended PT slabs. Scissor stair (L10 to Roof) | $275.0m |
| 15 May 2023 | Stage 14 - Level 7 & 8 Suspended Slabs | $275.0m |
| 15 May 2023 | Stage 15 - Construction of Level 9 & 10 Suspended Slabs. Construction of L11 to 34 Core Walls. Construction of L11 to underside of L34 Columns. Installation of Precast Concrete Façade & Cladding. Building Services B2-B1. | $275.0m |
| 15 May 2023 | Stage 16 - Tower Curtain Wall – EWS05, EWS09, EWS10 & EWS16 Ground Level to underside of Level 35 (Excluding works within the “Excluded Scope Markup” drawing and all façade doors). Vertical Transport & Ground - L1 Escalator. Inclusion of a performance solution supporting the destination controls serving passenger lifts. | $275.0m |
| 15 May 2023 | Stage 19 - Services from Levels 2 - 13 (inclusive), Fire Services alterations to L2, 7 and 8 voids. Excluding Level 11 & 12 Plant Rooms | $275.0m |
| 15 May 2023 | Stage 21 - Facde ESW-01 GRC; EWS-03/EWS -08 Soffits; EWS-07 Window Wall and EWS-10 Curtain Wall | $275.0m |
| 15 May 2023 | Stage 22 - Architectural Fit Out Basement 2, Basement 1, Levels 2 - 34. | $275.0m |
| 15 May 2023 | Stage 23 - Level 26 Suspended slab (Excluding Level 26 Hobs), Level 26 Precast Lid, Ground & Lower Ground Delay Pours, Columns above Level 34. | $275.0m |
| 15 May 2023 | Stage 25 - Level 28-34 Suspended Slabs | $300.0m |
| 15 May 2023 | Stage 26 - Building Services - Lower Ground, Ground & Level 1, Level 11 & 12 Plant Rooms & Levels 14-33 | $300.0m |
| 15 May 2023 | Stage 29 - Column Cladding, EWS-04, EWS-02, EWS-09 (Level 35 Steel) and Level 3, 10, 13 & 13 Terrace Doors. Excludes EWS-02 Bulkhead and Ground Floor Lobby Glazing. | $303.4m |
| 15 May 2023 | Stage 2 - Foundation piling, pile caps and core raft slab. | $275.0m |
| 15 May 2023 | Stage 30: Architectural Fit out of Lower Ground, Ground & Level 1, External Wet Areas of Lower Ground & Ground, Airlock between hydrant and substation, façade junction separation, fire pump room external door, reduced head height clearances, fire rated bulkhead to door DLG.20, EWS-02 fire rated bulkhead, intercom system to fire isolated staircases, diagonal sections of handrails with fire isolated staircases, fire separation between level 11 & 12 plant rooms. Excludes: Ground Floor Skylight, wheelchair lift, carpark and loading dock roller doors, services corridor to Ground floor south, fire booster cupboard doors, king street staircase tactile indicators, Link bridge to 567 Collins Street, statutory signage, terrace planter box, landscaping. | $303.4m |
| 15 May 2023 | Stage 32 - Level 35 & 36 Fitout & Finishes, Terrace Planters, L26 Concrete Screed, EWS-02 Interal Glass, EWS-02 Void Glass, L35 & L36 Hobs & Plinths, L35 Blockwork Certification. Excluding metalwork. | $303.4m |
| 15 May 2023 | Stage 33 - Façade Permit #4 including Access Davits, Roof Anchors, Rails, BMU Gate, Canopy Glass, EWS-13 Plant Roof Screen, EWS-15 Glazed Sky Lights & Roofing. Excluding Guttering to Canopy. | $303.4m |
| 15 May 2023 | Stage 34 - Wayfinding & Statutory Signage (Internal and External), Glazing Decals, Level 26 & 34 Blockwork, Wheelchair Lift, Landscaping, Door DG.39, King Street Stair Tactile Indicators, Services Corridor (Ground Floor South), Metalwork, excluding Carpark and Loading Dock Roller Doors. | $306.1m |
| 15 May 2023 | Stage 35: Level 2 Building Management Office | $306.1m |
| 15 May 2023 | Stage 3 - Hydostatic Basement 2 Slab & Inground Services | $0 |
| 15 May 2023 | Stage 4 -Core Walls & Columns from Basement 2 to the underside of Ground Floor | $0 |
| 15 May 2023 | Stage 5 - Basement Level 1 Suspended Slab, Basement Precast, Scissor Stair Precast and Fire Egress Stairs (to underside of Gr | $275.0m |
| 15 May 2023 | Stage 6 - Core structure ground to level 10 inclusive, and the precast scissor stairs ground to level 10 inclusive. | $275.0m |
| 15 May 2023 | Stage 7 - Lower ground floor suspended slab | $275.0m |
| 15 May 2023 | Stage 8 - Construction of the Ground Floor slab | $275.0m |
| 15 May 2023 | Stage 9 - External Precast Walls and Columns from Ground Floor to the underside of Level 11 | $275.0m |
| 21 Apr 2023 | Stage 35: Level 2 Building Management Office | $306.1m |
| 21 Apr 2023 | Stage 36: Miscellaneous Items including; - Services limited to Digital/LED Wall, Canopy Gutters, - L1 Storage Room (Architectural, Fire Services, Mechanical Services and Electrical Services). - External Doors limited to Collins St and King St Glazed Doors. - Landscaping limited to Landscaping Heater Pole and Collins St bench seating. - Signage limited to Totem and Landscape Signage. - Roller Doors limited to Automatic Roller Doors and Manual Roller Doors. | $306.1m |
| 25 Jan 2023 | Stage 1 - Level 1, 6 -13. Construction of an alteration of a building | $41.5m |
| 08 Nov 2022 | Stage 31 - Building Services Level 34, 35 & 36 | $303.4m |
| 05 Aug 2022 | Stage 28 - Level 36-37 Roof Steel, Level 35 Base Plates, LMR Beams, Level 35 LMR Precast Walls, L34 Terrace Precast Panel, Lift Shaft Precast Lids, Level 35 Core Lids, Level 35 Suspended Slab, Level 36 Composite Slab | $303.4m |
| 22 July 2022 | Stage 27 - All Core Walls above Level 34 including Wing Walls. Excluding Precase Lids & Cast-in-Plates | $300.0m |
| 31 May 2022 | Stage 24 - Level 27 Suspended Slab | $300.0m |
| 12 Apr 2022 | Stage 22 - Architectural Fit Out Basement 2, Basement 1, Levels 2 - 34. | $275.0m |
| 17 Feb 2022 | Stage 20 - Level 1 Canopy Steelwork and Level 11 - 12 Blockwork Walls. | $275.0m |
| 18 Jan 2022 | Stage 18 - Level 14 - 25 Suspended Slabs. Construction of a mixed-use office building | $275.0m |
| 15 Nov 2021 | Stage 17 - Level 11 – 13 (Inclusive) Suspended Slabs, Level 11 - 35 (Inclusive) Core Lobby Slabs, Level 12 & 13 Transfer Beams | $275.0m |
| 31 Aug 2021 | Stage 14 - Level 7 & 8 Suspended Slabs | $275.0m |
| 04 Aug 2021 | Stage 13 - Level 4 to Level 6 suspended PT slabs. Scissor stair (L10 to Roof) | $275.0m |
| 07 June 2021 | Stage 3 - Demolition of the Ground Floor and Basement Levels and Retention to the Existing Walls | $14.0m |
| 23 Apr 2021 | Stage 6 - Core structure ground to level 10 inclusive, and the precast scissor stairs ground to level 10 inclusive. | $275.0m |
| 20 Apr 2021 | Stage 5 - Basement Level 1 Suspended Slab, Basement Precast, Scissor Stair Precast and Fire Egress Stairs (to underside of Gr | $275.0m |
| 16 Feb 2021 | Stage 1 - Construction of a mixed-use office building. Retention, excavation and capping beams. | $275.0m |
| 31 May 2019 | Stage 2 - Demolition of a building from Ground floor to roof level (excluding ground floor slab and basement | $14.0m |
| 24 Apr 2019 | Demolition of existing building - Stage 1 - Partial internal strip out only as shown on the endorsed drawings | $715k |
| 19 June 2015 | Level 21, Proposed strip out & return to base building layout | $170k |
| 07 May 2009 | Proposed alterations to existing office tenancy | $250k |
| 02 Apr 2009 | Installation of ATM- NAB, facade. | $5k |
| 23 July 2008 | Installation of Exit Signs | $7k |
| 29 May 2008 | Office partition Level 9 South | $8k |
| 24 Aug 2007 | Installation of speed stiles to entry Ground Level | $10k |
| 24 Aug 2007 | Office fitout to Tenancy Levels 21 & 22 | $1.6m |
| 05 June 2007 | Staff Shop & Cafe fitout Ground Floor | $500k |
| 13 Feb 2007 | Staff Shop & Cafe fitout Ground Floor | $500k |
| 19 Oct 2006 | Stage 2: Office partition alterations on levels 1-9 and 12-20 (excluding fire hydrant and hose reel coverage on level 9). | $5.5m |
| 28 June 2006 | Stage 1: Office partition alterations on levels 10 & 11. | $4.5m |
| 29 Mar 2005 | Alterations to existing building signage | $11k |
| 04 Nov 2004 | Internal alterations to office Level 1 | $11k |
| 24 June 2004 | Relocation of Door Level 21 | $3k |
| 15 Dec 2003 | Internal fitout on level 4 | $2k |
| 01 Oct 2003 | Minor internal alterations to offices - Level 16 | $3k |
| 06 Aug 2003 | Internal office fitout. Level 22 | $15k |
| 04 Sept 2002 | Internal office fitout to existing building. Level 14, 555 Collins Street, Melbourne | $5k |
| 11 July 2002 | Level 3, 4 & 22 - Internal Office Fitout Alterations | $30k |
| 08 July 2002 | Levels 3 & 13 - Internal Office Alterations | $5k |
| 29 May 2002 | 5th Floor (part) - 6th Floor (Cytopia) Baker Buiding - Alteration Fitout. | $350k |
| 20 Dec 2001 | Alterations to existing building, office. | $120k |
| 08 Nov 2001 | Level 3 & 16 - Internal alteration to existing building. | $24k |
| 28 Sept 2001 | Level 20 & 22, internal alteration to existing building | $22k |
| 28 Sept 2001 | level 3, internal alteration to existing building | $13k |
| 28 Sept 2001 | Levels 2, 5, 20, internal alteration to existing building | $42k |
| 06 Dec 2000 | Alteration of a computer room, class 5, office. | $350k |
| 06 Sept 2000 | tenancy fitout of office layout. | $50k |
| 14 July 2000 | lvl 2 alteration to office | $5k |
| 16 Mar 2000 | construct standby generator room | $23k |
| 11 Mar 1999 | Alterations to a storeroom | $3k |
| 05 Nov 1998 | Tenancy fitout of office | $50k |
| 24 Mar 1998 | OFFICE FITOUT ON LEVEL 18 | $300k |
| 16 Apr 1997 | Internal tenancy alterations | $10k |
| 18 Mar 1997 | Installation of fire door | $2k |
| 17 July 1996 | Stage C8 - Tenancy fitout to office on Levels 9, 10 & 14 | $300k |
| 29 May 1996 | Office tenancy to Level 22 | $200k |
| 13 Dec 1994 | Alterations to Levels 7 and 12 | $300k |
Is Enterprise House - 555 Collins Street residential or commercial?
Enterprise House - 555 Collins Street is a commercial building. The City of Melbourne lists its main use as office.
When was Enterprise House - 555 Collins Street built?
Enterprise House - 555 Collins Street was completed in 2023.
How many floors does Enterprise House - 555 Collins Street have?
Enterprise House - 555 Collins Street has 35 floors above ground.
What businesses are in Enterprise House - 555 Collins Street?
The latest council census counted 8 businesses in Enterprise House - 555 Collins Street, including 555 Collins Exchange, ALLIANZ AUSTRALIA LIMITED and Amazon Pty Ltd.
Is there office or retail space for lease in Enterprise House - 555 Collins Street?
See the commercial listings on this page, or search this address on realcommercial.com.au and commercialrealestate.com.au.
Who designed and built Enterprise House - 555 Collins Street?
Charter Hall developed Enterprise House - 555 Collins Street, Gensler designed it and Lendlease built it. The building team section has the sources.
How tall is Enterprise House - 555 Collins Street?
About 145 metres, measured from the City of Melbourne's 3D building model. It's number 68 of 1596 buildings in Melbourne by height.
What public transport is near Enterprise House - 555 Collins Street?
Southern Cross Railway Station is the nearest train station, about 4 minutes' walk. The nearest tram stop is Southern Cross Station/Collins St #1, about 1 minute's walk.
What is the planning zone for Enterprise House - 555 Collins Street?
The site is in the Capital City Zone - Schedule 1 (CCZ1).
What was on the site before the tower was built?
The site previously held an earlier Enterprise House. The City of Melbourne approved its demolition in May 2019.
Has the building been sold or partly sold?
In August 2022, GIC bought a 50 per cent stake in 555 Collins Street.
Has any work been done on Enterprise House - 555 Collins Street recently?
The City of Melbourne has issued 80 building permits for Enterprise House - 555 Collins Street since 1994. The most recent was in April 2026.
Sources: City of Melbourne building permits (CC BY 4.0); CLUE building information (CC BY 4.0); CLUE business establishments (CC BY 4.0); Development Activity Monitor (CC BY 4.0); Geocoded National Address File (G-NAF) (Open G-NAF EULA (CC BY 4.0 based)). General information from public records, not legal, financial or building advice.