| Planning application | 2014 | Planning application TPM-2014-29 lodged |
| Approved | By 2016 | Planning permit granted (exact date not recorded) |
| Construction started | Sep 2016 | First major construction permit issued |
| First occupants | Dec 2020 | First occupancy permit issued |
| Completed | By Sep 2020 | The Olderfleet Building completed: 40 floors |
Each cost is the estimate on that record. Stages of a project often repeat its full value, so these don't add up to what was spent.
| 30 Jan 2026 | Stage 2 - Completion of Works | $1.8m |
| 26 Nov 2025 | Fitout Works to Office Tenancy Shell to Completion to Occupancy Permit (Work Club) | $350k |
| 20 Jan 2025 | Level 34 - Alterations to existing building -tenancy works to L34 | $204k |
| 26 Aug 2024 | Level 35 - Proposed Alterations to Existing Office | $50k |
| 08 Apr 2024 | Level 7 Olderfleet - Change of Use Of An Existing Gym To Office | $2k |
| 16 Jan 2024 | Internal Office Alterations | $320k |
| 22 Sept 2023 | Level 12 - Internal Office Fitout for AMC | $437k |
| 26 July 2023 | Level 38 - smoke detector alterations | $7k |
| 24 May 2023 | Internal Cova Office Fitout - Partial Level 7 Only | $931k |
| 08 Feb 2023 | Internal Cova Office Fitout - Partial Level 7 Only | $931k |
| 30 June 2022 | Ground Floor and Business Lounge - Olderfleet, P2 and P3 - Review of Occupancy Numbers | $1k |
| 10 June 2022 | Level 7 - Internal Office Fitout for Syra Resources | $484k |
| 13 May 2022 | Proposed alterations to exisiting retail tenancy. | $1.4m |
| 30 Mar 2022 | Level 7 Olderfleet - Change of Use Of An Existing Gym To Office | $2k |
| 17 Mar 2022 | Freja - 477 Collins - Stage 2 - Building works which includes remaining internal works and shall be read in conjunction with the existing building permit | $52k |
| 11 Jan 2022 | Olderfleet Building - Level 6 - Alterations to Child Care Tenancy | $20k |
| 25 Aug 2021 | Internal Office Fitout for CIP | $280k |
| 19 Jan 2021 | Tenancy 2 and 3 - Internal Office Fitout | $987 |
| 14 Dec 2020 | Commercial Gym Fitout | $0 |
| 10 Dec 2020 | MAM Office - Internal Fit out . Alterations to an existing building | $0 |
| 27 Nov 2020 | Level 9 - Salter Brothers Office fitout | $1.2m |
| 24 Sept 2020 | Level 12,13,14,15 - Alteration | $14.1m |
| 24 Sept 2020 | Stage 2 - Final - Conditional | $14.1m |
| 16 Sept 2020 | Stage 3 - including Fire Hydrants & Fire Hose Reels for P2 Business Lounge & Level 35, Fire Engineering, Regulation 129 & Removal of Two Office Doors on Level 35 | $4.4m |
| 16 Sept 2020 | Stage 4 - To permit remainder of proposed works only | $4.4m |
| 14 Sept 2020 | Alteration | $280k |
| 04 Sept 2020 | Level 33 - Olderfleet - FB Rice fitout - alteration | $4.0m |
| 28 Aug 2020 | Level 9 - Salter Brothers Office fitout | $1.2m |
| 10 Aug 2020 | Stage 2: Fire services | $4.0m |
| 23 July 2020 | Office Fit Out for Molino Cahill Lawyers | $1.4m |
| 13 July 2020 | Levels 16-17 - Internal Office Fitout for ServiceNow | $3.7m |
| 10 July 2020 | Tenancy P0.78. Retail Fitout of Existing Tenancy | $367k |
| 08 July 2020 | Stage 4 - To permit remainder of proposed works only | $4.4m |
| 03 July 2020 | Levels 10 & 11 - Stage 1 - All Works Excluding the Inter-tenancy Stair to Levels 10 and 11 and Hearing Augmentation System Installation | $4.5m |
| 01 July 2020 | Proposed Office Fitout at (Being at Lower Ground, Ground Level, Level 1,2,3,4, 5 & 35 | 477 Collins Street, Melbourne | $4.4m |
| 01 July 2020 | Stage 2 - To Permit Internal Non-Structural Fitout Works to Lower Ground & Ground Floor Only (Excluding All Works to Levels 1-5, Fire Hydrants & Fire Hose Reels to P2 Business Lounge & Level 35, Fire Engineering Retout Works to Lower Ground & Ground Floor Only | $4.4m |
| 29 May 2020 | Stage 1 - Architectural and services works associated with fit-out excluding Fire Hydrants, Fire Hose Reels & Community Hub Stepped Seating Areas | $64.2m |
| 29 May 2020 | Stage 2 - Fire Hydrants, Fire Hose Reels & Community Hub Stepped Seating Areas associated with fit-out | $64 |
| 29 May 2020 | Stage 3 - All works associated with Level 18 fit-out | $67.2m |
| 19 May 2020 | Stage 1: Levels 36, 37, 38 - Norton Rose Fulbright Melbourne Tenancy Fitout - Base Building Integration | $1.0m |
| 11 May 2020 | Levels 10 & 11 - Stage 2 - Final - Conditional | $4.9m |
| 06 May 2020 | Tenancy P03.08 & P03.09 - Construction of internal alterations to an existing building | $176k |
| 15 Apr 2020 | Tenancy L34.12, Level 34, - Alteration, Blackrock Fitout | $1.1m |
| 14 Apr 2020 | Stage 40 - Civil works to Collins Street and Flinders Lane, Shopfront to Flinders Lane | $300.0m |
| 31 Mar 2020 | Variation - Tenancy Split to L7, L9, L12 and L34 | $300.0m |
| 25 Mar 2020 | Code Black Coffee Shop Tenancy fitout & Kiosk fitout | $300k |
| 06 Mar 2020 | Levels 16-17 - Internal Office Fitout for ServiceNow | $3.7m |
| 07 Feb 2020 | Kid's Club Olderfleet - Internal Alteration - Fitout for new Child Care Centre | $2.5m |
| 29 Jan 2020 | Stage 2: Levels 36, 37, 38 - Norton Rose Fulbright Melbourne Tenancy Fitout - FINAL | $11.4m |
| 20 Nov 2019 | STAGE 38 - ARCHITECTURE AND SERVICES TO HERITAGE BUILDING | $300.0m |
| 11 Nov 2019 | STAGE 37 - STRENGTHENING TO HERITAGE BUILDING FLOORS | $300.0m |
| 29 Oct 2019 | STAGE 36 - BALUSTRADES TO STAIRS SERVING HERITAGE BUILDING AND TERRACES ON OFFICE FLOORS | $300.0m |
| 09 Oct 2019 | STAGE 35 - LEVEL 37 CANOPY AND BMU GARAGE | $300.0m |
| 12 Aug 2019 | STAGE 34 - LOBBY FITOUT WORKS - CONDITIONAL | $300.0m |
| 05 Aug 2019 | Stage 3 - All works associated with Level 18 fit-out | $67.2m |
| 23 July 2019 | Stage 33 - Level 39 to Roof Structure and Architecture Only - Conditional | $300.0m |
| 28 June 2019 | Stage 32 - Variation to EOT - Conditional | $300.0m |
| 16 Apr 2019 | STAGE 31 - PT SLABS LEVEL 33 TO 38 - CONDITIONAL | $300.0m |
| 08 Mar 2019 | STAGE 30 - CORE WALLS LEVELS 32 TO ROOF | $300.0m |
| 06 Mar 2019 | Stage 29 - PT Slabs Level 30 to 32 and Variation to PT Slabs Level 28 and 29 | $300 |
| 20 Feb 2019 | Stage 28 - Carpark Facade | $300 |
| 21 Dec 2018 | STAGE 27 – BASE BUILDING ARCHITECTURAL WORKS LEVELS 16-38 - CONDITIONAL | $300.0m |
| 12 Dec 2018 | STAGE 26 - ATRIUM LOBBY STRUCTURAL STEEL AND SKYLIGHTS - CONDITIONAL | $300.0m |
| 26 Nov 2018 | STAGE 25 - HERITAGE FLOORS STRUCTURAL AND STRENGTHENING WORKS - CONDITIONAL | $300.0m |
| 19 Oct 2018 | STAGE 24 - NZ CHAMBERS PRECAST WALL - CONDITIONAL | $300.0m |
| 16 Oct 2018 | STAGE 23 - BASE BUILDING ARCHITECTURAL WORKS LEVELS P0 TO 15 - CONDITIONAL | $300.0m |
| 04 Oct 2018 | Stage 22 - Remaining Precast - Conditional | $300.0m |
| 02 Oct 2018 | Stage 21 - Facade Levels 16 to Roof - Conditional | $300.0m |
| 22 Aug 2018 | Stage 20 - PT Slabs Levels 16 to 29 and Columns Levels 32 to 39 - Conditional | $300.0m |
| 02 Aug 2018 | Stage 19 - Services Levels 06 to Roof, Speedpanel and Masonry Levels 06 to Roof - Conditional | $300.0m |
| 27 July 2018 | Stage 17 - Heritage wall structural works - Conditional | $300.0m |
| 27 July 2018 | Stage 18 - Facade Levels 6 to 15 – Conditional | $300.0m |
| 29 May 2018 | Stage 16 - Repair to Heritage Wall - Conditional | $300.0m |
| 29 Mar 2018 | Stage 15 - PT Slabs L6-15 and P0 to P9 Masonry and Speedpanel Walls - Conditional | $300.0m |
| 15 Mar 2018 | Stage 14 - Core Walls and Columns Level 6-32 - Conditional | $300.0m |
| 15 Feb 2018 | Stage 13 - Services Levels P0 to P9 Excluding Carpark Mechanical Ventilation - Conditional | $300.0m |
| 03 Nov 2017 | Stage 12 - PT Slabs Levels P2 to P9, core walls levels P2-P9 - conditional | $300.0m |
| 01 Sept 2017 | Stage 11 - P1 Slab, Walls P0-O2 and Columns P0-P9 - Conditional | $300.0m |
| 03 July 2017 | Stage 10 - Levels PO (part) ans PO Mezzanine (part) slabs - conditional | $300.0m |
| 28 Apr 2017 | Stage 9 - In-ground services, piling & Ground Floor Slab excluding piling and excavation works adjacent to the adjoining property 47 William Street. | $300.0m |
| 07 Apr 2017 | Stage 8 - Demolition of Ground Floor Slab and Footings | $9.0m |
| 13 Jan 2017 | Stage 7 - Balance of Demolition Works | $8.8m |
| 01 Dec 2016 | Stage 6 - Partial demolition of office tower excluding eastern portion - Conditional | $6.8m |
| 18 Nov 2016 | Stage 5 - Internal Strip Outworks and Partial Deglazing of North and South Facade | $3.8m |
| 29 Sept 2016 | Stage 4 - Partial demoliton of carpark - Western portion | $3.3m |
| 22 Sept 2016 | New Building - Stage 3 - Slab Penetration For Roof Level | $800k |
| 15 Sept 2016 | New Building - Stage 2 - Demolition Enabling Works | $750k |
| 09 Sept 2016 | New Building - Stage 1 - Demolition Enabling Works (Internal Only) | $500k |
| 24 Oct 2013 | PROPOSED ALTERATIONS TO EXISTING RESTAURANT | $160k |
| 05 Sept 2013 | cafe fitout to existing tenancy Basement | $150k |
| 03 Sept 2012 | Architectural demolition works excluding services alterations Ground Floor | $200k |
| 09 Dec 2011 | Stage 2: Non-structural fitout works. Fitout to tenancy 'Lbrary Women Melbourne Pty Ltd' | $123k |
| 16 Nov 2011 | Fitout to tenancy 'Lbrary Women Melbourne Pty Ltd' | $23k |
| 28 Sept 2010 | Level 4-6 office Fitout Accenture Melbourne | $41k |
| 26 Aug 2010 | Stage 2: Remainder of works - office fitout alterations, Accenture Melbourne | $159k |
| 11 Dec 2009 | Proposed internal office fitout for Melbourne Conference & Training Centre | $500k |
| 02 Mar 2009 | Tenancy 3, Ground Floor 495 Collins Street | $120k |
| 04 Feb 2009 | Internal Alterations & Fitout - Suncorp GIO Branch | $463 |
| 07 Aug 2008 | Proposed external suncorp sky-signs and free standing Id-sign to existing facade/Ground. | $272k |
| 26 May 2008 | Allens Arthur Robinson. Office Internal Alterations to Ground Floor. | $150k |
| 02 Oct 2007 | CAP Gemini. Office fitout alterations to an existing building, Level 2 (part). | $10k |
| 06 Oct 2006 | Alterations- Tenancy Ground Floor | $180k |
| 03 Feb 2005 | Office partition alterations to existing tenancy on level 5, no 477 | $28k |
| 19 Apr 2004 | Office partition alterations Level 2 | $36k |
| 18 Feb 2004 | Tenancy works Level 2 | $19k |
| 02 June 2003 | Internal Alterations to an existing building on the Ground Floor. Allens Arthur Robinson | $50k |
| 28 Apr 2003 | Level 2 - Stage 2 - Works in Hertiage part of building | $200k |
| 19 Dec 2002 | Variation: Additional minor works - olderfleet building. Alterations to an existing office building, basement Level and Ground Level | $40k |
| 29 Nov 2002 | Additional minor works - olderfleet building. Alterations to an existing office building, basement Level and Ground Level | $40k |
| 22 Oct 2002 | Alterations to office - Ground Floor | $93k |
| 11 Sept 2002 | Level 1 - Stage 1 - Office Alterations Excludes works in heritage part of building | $200k |
| 23 Aug 2002 | Fit out to shop (Hairdressers/Beauty Salon) Ground & Upper levels | $80k |
| 04 Jan 2002 | Level 7 - Office alterations. | $100k |
| 13 Dec 2001 | Stage 1, partitions to an existing building. Levels 5 & 6. NRMA Insurance Ltd Office refurbishment | $200k |
| 31 Oct 2001 | Removal of fire hydrant lay flat canvas fire hoses. | $300 |
| 27 Sept 2001 | Stage 1- all building work to rear of levels 2 & 3. Office partition to levels 2 & 3 of The Olderfleet Building | $1.7m |
| 03 Aug 2001 | stage 1 strip out for reinstatement & upgrade of olderfleet heritage bldg | $268k |
| 27 July 2001 | Level 4 Office fitout for Allens Arthur Robinson. | $415k |
| 15 Jan 2001 | Stage 2 final alterations for reinstatement & upgrade of olderfleet heritage bldg | $5.1m |
| 30 Mar 2000 | Installation of alarm signalling equipment | $190 |
| 08 Oct 1999 | Alterations to Caffee Masters Ground Level | $93k |
| 06 Nov 1998 | Installation of exit door fail safe device | $1k |
| 02 Sept 1998 | Refurbishment and fitout an office on level 7 | $120k |
| 13 July 1998 | Internal alterations to level 1 | $5k |
| 30 June 1998 | Construct new wall and door | $3k |
| 30 June 1998 | Office alterations on level 4 | $1k |
| 12 Aug 1997 | Office fitout on the ground, 3 & 4 floors | $315k |
Is The Olderfleet Building residential or commercial?
The Olderfleet Building is a commercial building. The City of Melbourne lists its main use as office.
When was The Olderfleet Building built?
The Olderfleet Building was completed in 2020.
How many floors does The Olderfleet Building have?
The Olderfleet Building has 40 floors above ground.
What businesses are in The Olderfleet Building?
The latest council census counted 20 businesses in The Olderfleet Building, including Ashley Faithfull Training Studios Pty Ltd, Blackrock Investment Management (Aust) Limited and COPENHAGEN INFRASTRUCTURE PARTNERS.
Is there office or retail space for lease in The Olderfleet Building?
See the commercial listings on this page, or search this address on realcommercial.com.au and commercialrealestate.com.au.
Who designed and built The Olderfleet Building?
Mirvac developed The Olderfleet Building and William Pitt designed it. The building team section has the sources.
How tall is The Olderfleet Building?
About 168 metres, measured from the City of Melbourne's 3D building model. It's number 39 of 1596 buildings in Melbourne by height.
What public transport is near The Olderfleet Building?
Southern Cross Railway Station is the nearest train station, about 6 minutes' walk. The nearest tram stop is William St/Collins St #3, about 2 minutes' walk.
What is the planning zone for The Olderfleet Building?
The site is in the Capital City Zone - Schedule 1 (CCZ1).
Does The Olderfleet Building have an owners corporation?
Plan of subdivision TP820886 has 1 lot.
Has any work been done on The Olderfleet Building recently?
The City of Melbourne has issued 91 building permits for The Olderfleet Building since 1997. The most recent was in January 2026.
Sources: City of Melbourne building permits (CC BY 4.0); CLUE building information (CC BY 4.0); CLUE business establishments (CC BY 4.0); Development Activity Monitor (CC BY 4.0); Geocoded National Address File (G-NAF) (Open G-NAF EULA (CC BY 4.0 based)). General information from public records, not legal, financial or building advice.