| Completed | 1992 | 333 Collins Street completed: 33 floors |
Each cost is the estimate on that record. Stages of a project often repeat its full value, so these don't add up to what was spent.
| 21 Dec 2025 | Office Non-Structural Fit-Out | $50k |
| 17 Nov 2025 | Alterations to an Existing Building - 333 Collins Street - Stage 3: Level 5 External Terrace, Structural Works, Lift Works, Smoke Seals, Fire/Smoke Dampers, and Floor Boxes | $6.7m |
| 22 Oct 2025 | Alterations to an Existing Building - 333 Collins Street Stage 2: Fitout Works to Level 4 North, 5, 9, 11 and 23 (exc. Level 5 External Terrace, Level 12, 13, Structural Works, Lift Works, Smoke Seals, Fire/Smoke Dampers, and Floor Boxes/Lift Rebate Works) | $6.7m |
| 22 Sept 2025 | Level 14 - Alterations to an existing building | $10k |
| 12 Sept 2025 | Alterations to an Existing Building - 333 Collins Street Stage 1: Demolition/Internal Strip Out of Levels (Parts) 4, 5, 9, 11, 12, 13, and 23 & Partition Wall for Tenancy Split on Level 5 | $7.9m |
| 30 Oct 2024 | Level 5 - Tenancy fitout | $519k |
| 30 Sept 2024 | Level 5 - Tenancy fitout | $519k |
| 12 July 2024 | Level 5 - Internal alteration - Proposed Minor Internal Office Fitout | $194k |
| 05 July 2024 | Proposed Office Fitout - Internal alteration to existing building - Level 4 - project no: 2024320 | $228k |
| 16 Jan 2024 | Level 26, 333 Collins St - Office fitout works | $30k |
| 14 Dec 2023 | Stage 3 Level 22 Tenancy Alterations | $6.8m |
| 27 Nov 2023 | Stage 4 Level 21 Separable Portion 2B, Tenancy Alterations | $6.8m |
| 27 Nov 2023 | Stage 5 Level 21 Separable Portion 2C, Tenancy Alterations | $6.8m |
| 16 Nov 2023 | Stage 2 Level 21 Tenancy Alterations | $6.8m |
| 19 Sept 2023 | Stage 1 Level 20 Tenancy Alterations | $6.8m |
| 19 Sept 2023 | Stage 2 Level 21 Tenancy Alterations | $6.8m |
| 26 May 2023 | Tenancy 4 (L27 only) - Internal Fitout to existing office & tenancy only - Internal Non-Load Bearing/Structural only | $374k |
| 08 Feb 2023 | Tenancy 4 (L27 only) - Internal Fitout to existing office & tenancy only - Internal Non-Load Bearing/Structural only | $374k |
| 11 Nov 2022 | Level 15 - Alterations to existing office tenancy | $25k |
| 16 May 2022 | Stage 2: Fitout Works including Services Works | $1.2m |
| 28 Mar 2022 | Level 28 - Alterations and Fit-out (Kelly & Partners Melbourne) | $100k |
| 15 Apr 2021 | Level 10, Proposed Minor Internal Alterations Within Existing Office | $330k |
| 01 Feb 2021 | Level 27 - Installation of proposed deck. | $20k |
| 23 Dec 2020 | Level 7 - Strategem Minor Works - Alterations to Existing Office Tenancy | $11k |
| 13 Nov 2020 | Levels 20-22 - Internal Alterations to Existing Offices for Arnold Bloch Leibler | $459k |
| 06 Oct 2020 | Level 7. Internal office alterations | $7k |
| 03 July 2020 | Level 7. Internal office alterations | $7k |
| 13 May 2020 | Stage 1: Male Facilities Works only, excluding Fire Services | $708k |
| 13 May 2020 | Stage 2: Male Facilities Fire Services only | $708k |
| 25 Feb 2020 | Part Level 26 - Mushan Office - Internal Office Alterations | $85k |
| 29 Jan 2020 | Levels 20-22 - Internal Alterations to Existing Offices for Arnold Bloch Leibler | $459k |
| 15 Aug 2019 | Level 10 - Slade Group - Office tenancy fit-out | $30k |
| 27 Mar 2019 | Level 4 - Office alteration | $37k |
| 20 Mar 2019 | Level 3 Office Partition Alteration | $27k |
| 14 Mar 2019 | Level 24 - Alterations to existing Office | $39k |
| 20 Dec 2018 | Level 11 - Stage 1 - All Works Excluding Services - Tenancy Fit-Out of Office (Noah Holdings) | $180k |
| 06 Dec 2018 | Proposed showroom fitout for "Aspect Furniture" | $240k |
| 20 Nov 2018 | Level 15 - Proposed alterations to existing office tenancy | $610 |
| 15 Nov 2018 | Alterations to existing building | $119 |
| 21 Sept 2018 | Level 5- Office fitout | $180k |
| 01 Aug 2018 | Level 15 - Alterations to existing building | $41k |
| 24 July 2018 | Stage 3 - Level 11 (Part) - Tenancy Fit-Out of Office | $264k |
| 20 July 2018 | Proposed Internal Office Fitout for Kelly & Partners | $175k |
| 02 July 2018 | Level 3 - Office Fitout | $0 |
| 27 June 2018 | Level 6 - Fitout to office | $22k |
| 18 June 2018 | Proposed Internal Office Fitout for Kelly & Partners | $175k |
| 08 June 2018 | Level 11 - Proposed fitout of existing office | $130k |
| 07 June 2018 | Office fitout - Level 3 | $20k |
| 13 Apr 2018 | Level 9 - Existing Office Tenancy Reception Area on Level 9 for GPPM International | $48k |
| 09 Apr 2018 | Stage 2 - Balance of Works Excluding Fire Hydrants | $290k |
| 05 Mar 2018 | Level 20 - Office Alterations | $75k |
| 14 Nov 2017 | Stage 2: Level 11 - Fire Services | $1.3m |
| 27 Oct 2017 | Level 11 - Custom Fleet & Architectural & Services works excluding Fire Services & Office Fit-Out | $1.3m |
| 16 Oct 2017 | Level 10 - Internal office alterations Mason Black Lawyers | $150k |
| 06 Oct 2017 | Level 4 - Recoveries Corp - Internal office alterations | $200k |
| 21 Sept 2017 | Level 20 - Office Fitout | $87k |
| 07 Sept 2017 | Level 5 - Tenancy fit out | $2.7m |
| 17 Aug 2017 | Alteration to Existing Office being Front of House Upgrade Works and Construction of Decking | $842k |
| 17 Aug 2017 | Level 5 Decking | $81k |
| 14 Aug 2017 | Level 14 - Proposed Internal Office Fitout for VCSO | $450k |
| 10 Aug 2017 | Stage 2: Male Facilities Fire Services only | $708k |
| 27 June 2017 | Level 9 OFFICE FITOUT | $15k |
| 06 June 2017 | Level 15 - Relocation of Wall and Sprinklers | $7k |
| 26 May 2017 | Level 7 - Proposed Internal Office Fit-out | $660k |
| 27 Mar 2017 | Stage 1 : Alterations to Levels 20 & 21 only, excluding Level 22 - Proposed alterations to existing office tenancy | $204k |
| 27 Mar 2017 | Stage 2: Alterations to Level 22 | $204k |
| 19 Jan 2017 | Stage 4 - Installation of a smoke damper and repairs to existing smoke lobby walls above the ceiling | $13.4m |
| 22 Dec 2016 | Ground floor - Internal Office Fit-out for Sneakerboy HQ Permit Cancelled - refer DM #10903190 | $100k |
| 09 Nov 2016 | Stage 2 - Proposed Internal Office Fitout for HSBC & Sublet Area (Base Building) | $1.8m |
| 27 Oct 2016 | Level 10 - Proposed office itout for HSBC | $1.5m |
| 19 Sept 2016 | Stage 1: All works excluding operable wall to Boardroom 3 | $469k |
| 19 Sept 2016 | Stage 2 - Operable Wall to Boardroom 3 | $469k |
| 24 Aug 2016 | Stage 4 - Installation of a smoke damper and repairs to existing smoke lobby walls above the ceiling | $13.4m |
| 21 July 2016 | Stage 2 - Operable Wall to Boardroom 3 | $469k |
| 15 July 2016 | Stage 3 - Tenancy fitout and connection of 3 levels with stair. Structural Steel, Stair Penetration, Joinery, Stair Finish | $11.4m |
| 11 July 2016 | Stage 1: All works excluding operable wall to Boardroom 3 | $469k |
| 21 June 2016 | Level 9, South Tenancy - Office tenancy fitout | $30k |
| 15 June 2016 | Stage 2: As shown on the approved plans | $11.4m |
| 09 June 2016 | Stage 2: Alterations to Level 22 | $204k |
| 16 May 2016 | Levels 17,18 &19 - Tenancy fitout and connection of 3 levels with stair | $9.0m |
| 13 May 2016 | Level 9 - Office Fitout | $15k |
| 11 Feb 2016 | Level 22- ARNOLD BLOCH LEIBLER - OFFICE ALTERATIONS | $158k |
| 20 Jan 2016 | Level 20 - Office Alterations - Arnold Block Leibler | $169k |
| 12 Jan 2016 | Level 10 - Change of use to training school | $153k |
| 22 Dec 2015 | Level 26 - Fitout of office | $244k |
| 28 Oct 2015 | Level 28 - Proposed Internal Office Fitout for La Trobe Financial | $277k |
| 22 Sept 2015 | Level 7 (East) - Internal office fit out - partial | $44k |
| 03 Sept 2015 | Stage 1 - Level 26 - Alterations to an existing building | $96k |
| 17 June 2015 | Internal Alterations to Fan Facilities Space, Lot 1 333 Collins St, Melbourne | $520k |
| 12 June 2015 | Level 25 - Proposed Internal Office Fitout | $147k |
| 16 Apr 2015 | Installation of new ASE (Code Red) monitoring system | $1k |
| 13 Apr 2015 | Level 20 - Alterations to existing office tenancy | $143k |
| 30 Oct 2014 | Level 19 - Office Tenancy Establishment Works | $30k |
| 14 Oct 2014 | Level 4 alterations to existing office | $76k |
| 10 Sept 2014 | Level 20, Proposed alterations to existing office tenancy | $190k |
| 28 Aug 2014 | Level 7, Internal office fit out. | $150k |
| 19 Aug 2014 | Level 18 Office fit out | $60k |
| 08 Aug 2014 | Level 3, Office Fit Out | $374k |
| 05 Aug 2014 | Level 8 office fitout | $519k |
| 28 Oct 2013 | Office fit out Level 28 | $30k |
| 10 Sept 2013 | OFFICE ALTERATIONS TO SHOWERS LEVEL 16 | $96k |
| 06 Sept 2013 | Internal Alterations to an existing office - Level 13 | $7k |
| 23 Aug 2013 | Office fitout Level 27 | $79k |
| 15 July 2013 | Proposed Office Tenancy establishment works - Level 8 | $32k |
| 06 May 2013 | Office Fit Out Level 19 | $17k |
| 03 Apr 2013 | Alterations to Office Building - Level 19 - New Meeting Rooms | $253k |
| 17 Jan 2013 | Alterations to sprinkler system Level 6 (PART) | $19k |
| 04 Oct 2012 | Office fitout and alterations to Level 4 | $33k |
| 25 Sept 2012 | Office Partitioning - Level 7 | $670k |
| 27 July 2012 | Office fitout - Level 3 | $1.8m |
| 01 June 2012 | Fitout Level 4 (BCA 2011) | $2.8m |
| 09 May 2012 | Internal alterations to Fitout of Offices - Ground, Level 6, Level 9 | $318k |
| 10 Nov 2011 | Fitout Level 4 (BCA 2011) | $55k |
| 07 Oct 2011 | Tenancy Fitout Works Level 23 | $217k |
| 30 Sept 2011 | Office fitout Levels 21 & 22 - Office Fitout | $6.5m |
| 09 Sept 2011 | Refurbishment Male & Female change rooms | $75k |
| 30 June 2011 | Proposed Alterations De-Fit to Level 3&4 | $340k |
| 07 June 2011 | Internal office alterations Level 2 | $272k |
| 16 Mar 2011 | Office partitioning on level 7, 333 Collins Street, Melbourne | $15k |
| 28 Jan 2011 | Level 11 - Office partition alterations to existing tenancy | $39k |
| 03 Dec 2010 | DEUTSCHE BANK MELBOURNE - MINOR ALTERATIONS | $50k |
| 12 Nov 2010 | Internal additions/Alterations to office - Level 7 | $7k |
| 12 Aug 2010 | Alterations Level B2 W C's | $50k |
| 04 Aug 2010 | Proposed office alterations to level 10 | $9k |
| 07 July 2010 | Internal Tenancy Fitout of an office on level 25 | $171k |
| 03 May 2010 | Level 2, 333 Collins St: Internal office fitout. | $2.2m |
| 23 Apr 2010 | Level 2, 333 Collins St: Internal office fitout. | $2.2m |
| 12 Apr 2010 | 333 Collins Street Lvl 2: Demolition of internal non-load-bearing partition walls (office) | $50k |
| 02 Dec 2009 | Office fitout alteration works to an existing building Level 7 | $70k |
| 22 July 2009 | Variation #3: Construction of a New Building - Fitout Works | $22.5m |
| 29 Apr 2009 | Construction of minor alterations to the existing office tenancy - NOMURA, Level 25 | $41k |
| 30 Mar 2009 | Proposed installation of new workstations to existing office tenancy Level 24. | $45k |
| 26 Sept 2008 | Level 10 office alterations Suite 1006 | $15k |
| 24 July 2008 | Alteration to offices, tenancy fitout of offices, internal re-fit only, Level 3 Lot 3. | $71k |
| 24 June 2008 | Construction of a New Building - Fitout Works | $21 |
| 24 Apr 2008 | Internal alterations to level 14 | $31k |
| 04 Mar 2008 | Candle CT Talent Specialists. Office Fitout Alterations to an Existing Building Level 14 (Part). | $32k |
| 19 Feb 2008 | Office fitout, Ground First and Fifth floors. | $2.8m |
| 19 Dec 2007 | Office refurbishment to Level 23. | $2.0m |
| 07 Nov 2007 | Fitout to commercial offices on Level 4. | $65k |
| 07 Nov 2007 | Office fitout Mezzanine (Level 4). | $60k |
| 19 Oct 2007 | Additions/Alterations to existing building, Level 6 office fitout. Stage 1: Demolition only. | $355k |
| 21 Sept 2007 | Architectural and services works to office Level 23. | $2.0m |
| 10 Sept 2007 | Office fitout Level 24 | $1.5m |
| 03 Aug 2007 | Demolition works to office Level 23. | $2.0m |
| 16 May 2007 | Alterations to Deutsche Bank office, Level 1. | $186k |
| 14 May 2007 | Office fitout to Level 5. | $1.3m |
| 27 Apr 2007 | Alterations to office building, tenancy fitout to Level 8, Lot 804. | $20k |
| 18 Apr 2007 | Alteration to offices, demolition of internal walls only, Level 3 Lot 3. | $22k |
| 13 Mar 2007 | Office Fitout on level 7 | $60k |
| 28 Feb 2007 | Constructuion-Commercial offices for (Link Market Services) Level 9 | $760k |
| 16 Jan 2007 | Office fitout to Level 9. | $30k |
| 19 Dec 2006 | Alterations to existing teaching facility, level 9. | $9k |
| 25 July 2006 | Internal alteration-Level 5 | $370k |
| 15 June 2006 | Clayton Utz Tenancy Fitout to Levels 16, 17, 18 and 19. Stage 3: Level 17 (part) - Variation works only. | $3.0m |
| 09 June 2006 | Upgrade of EWIS | $239k |
| 01 June 2006 | Alterations - Fitout LEVEL 28 | $106k |
| 18 May 2006 | Office fitout, alterations on Level 25. | $60k |
| 21 Apr 2006 | Stage 2 - Office building levels 17, 18 and 19 works only - conditional; Clayton Utz tenancy fitout. Office building level 16 & level 18 (part) (excluding eastern end meeting rooms) | $3.0m |
| 14 Dec 2005 | Stage 1: Alterations to office building level 16 works only conditional. Clayton Utz tenancy fitout | $3.0m |
| 08 Nov 2005 | office fitout | $220k |
| 21 Oct 2005 | Stage 2:Facade work- Level 16 | $76k |
| 23 Sept 2005 | Stage 1: office fitout alterations to an existing building | $2.6m |
| 23 Aug 2005 | Variation - minor works to Area 2 Offices | $30k |
| 17 Aug 2005 | Level 8, 327/343 Collins St, Melb office fitout | $6k |
| 01 Aug 2005 | Office fitout alterations to an existing building | $210k |
| 08 July 2005 | (part) level 16 offices - stripout of shaded area as indicated on approved plans | $98k |
| 23 June 2005 | Ofice building infill slab/ level 16 | $76k |
| 22 June 2005 | Stage 2: office fitout works | $1.9m |
| 10 June 2005 | Minor alterations Part Level 1 | $15k |
| 14 Apr 2005 | proposed internal alterations to level 25 (part) | $798k |
| 19 Oct 2004 | Tenancy fitout of offices Level 2 | $15k |
| 16 Aug 2004 | Tenancy fitout of offices | $11k |
| 10 Aug 2004 | Internal fitout works Ground floor | $32k |
| 31 May 2004 | Level 24, Office alterations to Deutsche Bank | $40k |
| 17 Mar 2004 | stage 1 Alterations to building. Internal alterations to Level 20,21& 22 | $2.0m |
| 25 Feb 2004 | Alterations to internal office level 4 | $50k |
| 01 Dec 2003 | Internal alterations to levels 17, 18 & 19 (office) Clayton Utz tenancy. | $235k |
| 19 Nov 2003 | Alteration to Sprinkler Heads for Minor Internal Building Works - Level 1 | $4k |
| 30 Oct 2003 | Internal alterations on Level 26 | $200k |
| 21 Oct 2003 | Office fitout alterations to an existing building - Level 7 (Part A) | $8k |
| 15 Aug 2003 | Tenancy fitout of offices and alterations to reception. Level 10 | $52k |
| 07 Aug 2003 | Level 25- Reinstate Base Design | $221k |
| 12 Feb 2003 | Level 22- Office Alterations | $12k |
| 29 Jan 2003 | Alterations to existing office tenancy including new external deck. | $89k |
| 10 Jan 2003 | Office alterations to existing building. Level 23 - Deutsche Bank | $20k |
| 01 Aug 2002 | Level 24 - Office Fitout | $9k |
| 28 May 2002 | Office fitout level 7 | $15k |
| 05 Apr 2002 | Levels 16 & 17 - Office Alterations | $624k |
| 22 Feb 2002 | Level 1 - Office Alterations. | $25k |
| 18 Sept 2001 | Level 24 Alteration to offices for Deutsche Bank | $17k |
| 11 July 2001 | Part level 20,21 & 22 office alterations for Arnold Block Leibler | $500k |
| 26 Mar 2001 | Office partition alterations level 6. | $13k |
| 20 Feb 2001 | lvl 23 office fit out | $150k |
| 08 Nov 2000 | Office fitout on level 20 Building known as 333 Collins Street | $80k |
| 25 Sept 2000 | non-structural alts & revised fit-out of existing restaurant. | $50k |
| 13 Sept 2000 | LEVEL 3, Office fitout for Clayton Utz | $490k |
| 13 Sept 2000 | lvl 6 dispensation to allow reduced width of path of travel | $1k |
| 20 June 2000 | Level 19 Clayton Utz Tenancy | $200k |
| 11 Apr 2000 | Alterations to tenancy and removal of existing hydrant hoses on ground level | $60k |
| 04 Apr 2000 | New Cable Risers throughout the building | $437k |
| 25 Aug 1999 | Internal alterations to parts of levels 17, 18 & 19 | $1.3m |
| 20 July 1999 | Tenancy fitout on level 5 note cfi not dated | $140k |
| 28 Dec 1998 | Office fitout level 28 | $100k |
| 29 Oct 1998 | Office fitout level 4 | $870k |
| 22 Oct 1998 | Office alterations on level 4, 333 Collins Street, Melbourne for Coopers & Lybrand Telstra Float | $9k |
| 01 Sept 1998 | Fitout of office | $350k |
| 28 Aug 1998 | Office alterations on level 6 (north), 333 Collins Street, Melbourne | $25k |
| 20 July 1998 | Internal alterations to level 25 | $491k |
| 13 Jan 1998 | partition fitout | $187k |
| 08 Dec 1997 | Office fitout on Level 5 | $210k |
| 11 Nov 1997 | Alterations & additions | $500k |
| 09 Oct 1997 | Alterations on Level 6 North building, 333 Collins Street, Melbourne | $20k |
| 12 June 1997 | Alterations | $300k |
| 03 Apr 1997 | Creation of lift shift openings | $13k |
| 21 Mar 1997 | Fitout to St George bank | $1.7m |
| 12 Dec 1996 | Alterations to office partitions on Levels 21 & 22 | $100k |
| 18 Nov 1996 | Internal office alterations | $80k |
| 24 Oct 1996 | Alterations to offices | $3.8m |
| 10 Oct 1996 | Alterations to Floors 1 & 5 | $140k |
| 25 Sept 1996 | Level 7 office fitout | $120k |
| 03 July 1996 | Partition fitout | $579k |
| 25 Mar 1996 | Internal alterations | $518k |
| 25 Mar 1996 | Offices fitout Levels 9 & 10 | $1.1m |
| 22 Dec 1995 | Office fitout Levels 5 & 6 | $750k |
| 20 Dec 1995 | Alterations | $539k |
| 23 Oct 1995 | Part demolition of Levels 12, 13 and 15 | $20k |
| 12 Oct 1995 | Tenancy fitout | $1.8m |
| 23 Feb 1995 | Tenancy fitout | $10.0m |
Is 333 Collins Street residential or commercial?
333 Collins Street is a commercial building. The City of Melbourne lists its main use as office.
When was 333 Collins Street built?
333 Collins Street was completed in 1992.
How many floors does 333 Collins Street have?
333 Collins Street has 33 floors above ground.
What businesses are in 333 Collins Street?
The latest council census counted 44 businesses in 333 Collins Street, including Affinity Private Advisors Pty Ltd, Allfin and Altitude Recruitment.
Is there office or retail space for lease in 333 Collins Street?
See the commercial listings on this page, or search this address on realcommercial.com.au and commercialrealestate.com.au.
Who designed and built 333 Collins Street?
Becton Corporation developed 333 Collins Street and Robert Peck von Hartel Trethowan designed it. The building team section has the sources.
How tall is 333 Collins Street?
About 118 metres, measured from the City of Melbourne's 3D building model. It's number 92 of 1596 buildings in Melbourne by height.
What public transport is near 333 Collins Street?
Flinders Street Station is the nearest train station, about 4 minutes' walk. The nearest tram stop is Elizabeth St/Collins St #5, about 1 minute's walk.
What is the planning zone for 333 Collins Street?
The site is in the Capital City Zone - Schedule 1 (CCZ1).
Has any work been done on 333 Collins Street recently?
The City of Melbourne has issued 156 building permits for 333 Collins Street since 1995. The most recent was in November 2025.
Sources: City of Melbourne building permits (CC BY 4.0); CLUE building information (CC BY 4.0); CLUE business establishments (CC BY 4.0); Geocoded National Address File (G-NAF) (Open G-NAF EULA (CC BY 4.0 based)). General information from public records, not legal, financial or building advice.