That's Built · Building report

Paragon

318 Queen Street, Melbourne VIC 3000
Generated 8 November 2026
Residential · Residential Apartment
166 mheight
48floors
2021completed
227homes
14permits

Development milestones

Planning application2011Planning application TPM-2011-24 lodged
ApprovedBy 2018Planning permit granted (exact date not recorded)
Construction startedJun 2018First major construction permit issued
First occupantsFeb 2021First occupancy permit issued
CompletedBy Jun 2021Paragon completed: 48 floors

Building team

Developer
Beulah International
Architect
Fender Katsalidis
Builder
Multiplex
Landscape architect
Paul Bangay

Planning & subdivision

Zone
CCZ1
Overlays
DDO1, DDO10, PO1
Strata plan
PS637192 · 228 lots
Scores
🚆 8 · ☕ 6 · 🌳 7 · ✨ 9

Timeline

9 Feb 2026Office levels at former Celtic Club site sold; Paragon base
In February 2026 the entity which took possession of the former Celtic Club site at 316-320 Queen Street from the developer sold levels 1-3 beneath Paragon, with the space to be repurposed as offices.
20231 building permit · about $400k of new works
Largest: Level 4 - construction to office fitout
2022Council census records it as residential apartment, 50 floors
Name recorded: Paragon
30 Jun 2021Multiplex completes Paragon tower
In mid-2021 Multiplex announced completion of the $200 million, 48-level Paragon tower with 227 apartments, which stands 167 metres above street level. Beulah's executive director commented on the milestone.
By Jun 2021Paragon completed: 48 floors
Derived from The Property Tribune
Feb 2021First occupancy permit issued
Derived from City of Melbourne building permits
202114 certificates
Largest: Stage 10 Architectural shell: basement 02 to level 04, Building services (excluding fire) basement 02 to level 04, Facade level 01 to level
23 Sep 2020Paragon tops out
A September 2020 report said the Paragon tower had topped out the previous month, with 48 storeys and 227 apartments. Construction was continuing through pandemic restrictions.
20201 building permit
Largest: Stage 17 - Level 34 to 44 PT Slabs
20195 building permits
Largest: Stage 12 - Remainder of Services Works
By 2018Planning permit granted (exact date not recorded)
Derived from City of Melbourne Development Activity Monitor
30 Nov 2018Paragon site works and demolition progress
Beulah's November 2018 construction update said site preparation, demolition and enabling works were progressing, with the remaining old building demolished that month and Multiplex installing the basement retaining wall. The update was published by the developer.
30 Sep 2018Beulah and Multiplex break ground at Paragon
Beulah International and Multiplex broke ground on the $200 million Paragon project in late September 2018. The article said the historic Celtic Club facade was to be retained and restored, and that the tower would have 227 apartments across 48 levels.
4 Aug 2018Multiplex appointed as builder for Paragon
In August 2018 Beulah International appointed Multiplex as builder for the $200 million Paragon project, described as 227 apartments over 48 levels.
Jun 2018First major construction permit issued
Derived from City of Melbourne building permits
2018Council census records it as unoccupied - under construction, 1 floors
Name recorded: The Celtic Club
20183 building permits · about $109.1m of new works
Largest: Stage 5 - Slab on Ground and In Ground Civil Services
12 Apr 2017Former Celtic Club site set to proceed as Paragon
Reporting in April 2017 said the former Celtic Club site at 316-320 Queen Street was poised to proceed as Paragon, a 48-level tower under an approval for 256 apartments that was expected to change. The architect was reported as Fender Katsalidis.
2014Council census records it as office, 4 floors
Name recorded: The Celtic Club
20121 building permit · about $28k of new works
Largest: Fire service alterations
2011Planning application TPM-2011-24 lodged
Derived from City of Melbourne Development Activity Monitor
2009Council census records it as entertainment/recreation - indoor, 4 floors
Name recorded: The Celtic Club
20071 building permit · about $111k of new works
Largest: Alterations-New outdoor terrace smoking area-Ground floor
20032 building permits · about $170k of new works
Largest: Internal alteration to Celtic Club
2002First council census entry: entertainment/recreation - indoor, 4 floors

Building permits and certificates (28)

Each cost is the estimate on that record. Stages of a project often repeat its full value, so these don't add up to what was spent.

28 Feb 2023Level 4 - construction to office fitout$400k
26 Feb 2021Stage 10 Architectural shell: basement 02 to level 04, Building services (excluding fire) basement 02 to level 04, Facade level 01 to level 16$109.1m
26 Feb 2021Stage 13 - Floor Slabs Level 26 to 33$109.1m
26 Feb 2021Stage 14 - Remainder of Architectural Works$109.1m
26 Feb 2021Stage 15 - level 25 pt slab$109.1m
26 Feb 2021Stage 16 - Remainder of Facade Works$109.1m
26 Feb 2021Stage 18 - Remainder of structural works.$109.1m
26 Feb 2021Stage 19 - Levels 48 and 49 suspended slabs, fire pump room structural steel and damper tanks.$109.1m
26 Feb 2021Stage 20 - Final. Remainder of works and miscellaneous updates$109.1m
26 Feb 2021Stage 3 - retention and foundation piling and capping beams$109.1m
26 Feb 2021Stage 4 - excavation of basement and basement raft slab$109.1m
26 Feb 2021Stage 5 - Slab on Ground and In Ground Civil Services$109.1m
26 Feb 2021Stage 5 - variation to pile design$109
26 Feb 2021Stage 8 - Levels 2 to 5 Slabs and remaining levels core walls, columns and stairs$109.1m
26 Feb 2021Variation to Protection Works$109.1m
16 Mar 2020Stage 17 - Level 34 to 44 PT Slabs$109.1m
15 Nov 2019Stage 12 - Remainder of Services Works$109.1m
20 Sept 2019Stage 11- Floor Slabs- Levels 8-24$109.1m
27 June 2019Stage 9 - Level 6 & 7 Floor Slabs, Structural Steelwork and Blockwork$109.1m
29 Mar 2019Stage 7 - Basement level 1, Basement Mezzanine and Level 1 Slabs - Conditional$109.1m
01 Mar 2019Stage 6 - Insitu columns and core walls up to and including level 7 and insitu stairs up to and including level 4$109.1m
20 Dec 2018Stage 5 - Slab on Ground and In Ground Civil Services$109.1m
04 Oct 2018Stage 2 - Foundation Piling$109.1m
29 June 2018Stage 1: Demolition works excluding heritage Facade - New Building (Paragon)$109.1m
27 Mar 2012Fire service alterations$28k
03 Sept 2007Alterations-New outdoor terrace smoking area-Ground floor$111k
24 Dec 2003Construction of new toilet facilites & facade works$80k
01 May 2003Internal alteration to Celtic Club$90k

Questions and answers

Is Paragon residential or commercial?
Paragon is a residential building. The City of Melbourne lists its main use as residential apartment.

When was Paragon built?
Paragon was completed in 2021.

How many floors does Paragon have?
Paragon has 48 floors above ground.

How many apartments are in Paragon?
Paragon has 227 homes. The national address file lists 229 unit addresses here, and some of those can be shops or offices.

What size apartments are in Paragon?
The City of Melbourne's development record lists 33 1 bed, 170 2 bed and 24 3+ bed apartments. The built numbers may differ a little.

Does Paragon have parking?
The City of Melbourne records 20 residential car spaces at this property. Which apartments have a space isn't recorded, so check the listing.

What do apartments cost near Paragon?
The median unit price in Melbourne was $545,000 in 2025, from the Victorian Property Sales Report. That's for the whole suburb, not this building.

Are there apartments for sale or rent in Paragon?
See the residential listings on this page, or use the shortcuts to search 318 Queen Street on realestate.com.au and Domain.

Who designed and built Paragon?
Beulah International developed Paragon, Fender Katsalidis designed it and Multiplex built it. The building team section has the sources.

How tall is Paragon?
About 166 metres, measured from the City of Melbourne's 3D building model. It's number 40 of 1596 buildings in Melbourne by height.

What public transport is near Paragon?
Melbourne Central Station is the nearest train station, about 4 minutes' walk. The nearest tram stop is Melbourne Central Station/La Trobe St #5, about 2 minutes' walk.

What is the planning zone for Paragon?
The site is in the Capital City Zone - Schedule 1 (CCZ1).

Does Paragon have an owners corporation?
Plan of subdivision PS637192 has 228 lots.

Have any parts of the Paragon site been sold?
Yes. In February 2026, office levels at the former Celtic Club site, the Paragon base, were sold.

Has any work been done on Paragon recently?
The City of Melbourne has issued 14 building permits for Paragon since 2003. The most recent was in February 2023.

Sources: City of Melbourne building permits (CC BY 4.0); CLUE building information (CC BY 4.0); CLUE residential dwellings (CC BY 4.0); Development Activity Monitor (CC BY 4.0); Geocoded National Address File (G-NAF) (Open G-NAF EULA (CC BY 4.0 based)). General information from public records, not legal, financial or building advice.