| Planning application | 2015 | Planning application TPM-2015-13/A lodged |
| Approved | By 2021 | Planning permit granted (exact date not recorded) |
| Construction started | Jul 2021 | First major construction permit issued |
| First occupants | Sep 2023 | First occupancy permit issued |
| Completed | 2023 | Meriton completed: 58 floors |
Each cost is the estimate on that record. Stages of a project often repeat its full value, so these don't add up to what was spent.
| 14 Feb 2024 | SHOP 1, 140 KING ST - PROPOSED ALTERATIONS TO EXISTING RETAIL SHOP | $165k |
| 25 Sept 2023 | Stage 1 - Construction of a new mixed use development over 57 storeys | $0 |
| 25 Sept 2023 | Stage 2 - Basement Structure & In-Ground Services | $0 |
| 25 Sept 2023 | Stage 6 - ground to level 2 wall lining, amenities, facade & signage | $108.5m |
| 26 July 2023 | Stage 8 – Balance of Works (including paving landscaping and services) | $108.5m |
| 03 July 2023 | Stage 8 – Balance of Works (including paving landscaping and services) | $108.5m |
| 14 Apr 2023 | Stage 7 - L57 to Roof (Architectural, Structural, including crown framing, signage and cladding, Services), Substation fire rated cover. | $108.5m |
| 10 Mar 2022 | Stage 5 – L14-L58, Architectural excluding GF and L2, wall linings and signage | $108.5m |
| 22 Dec 2021 | Stage 4 – Services (B2 – L13), Lifts, Façade (L3 – L57), Structural (L14 – L57) | $108.5m |
| 27 July 2021 | Stage 3 – Structural - Ground Floor to Level 13 (core, slabs and vertical) | $108.5m |
| 20 May 2020 | Stage 1 - Construction of a new mixed use development over 57 storeys | $0 |
| 29 Apr 2020 | Demolition of Existing Building | $479k |
| 18 Oct 2010 | Office tenancy fitout (Barbara Sterner Recruitment) | $45k |
| 30 Sept 2009 | Retail Tenancy fitout to shop | $150k |
| 03 June 2004 | Office fitout to level 2 - Intergrated management resources | $150k |
| 12 Nov 2001 | Stage 1 - Alterations to an existing building. Architectural. | $83k |
| 25 Oct 2001 | Alterations to building, installation of exit and emergency lighting | $7k |
| 02 Oct 1997 | Fitout for the food outlet | $45k |
Is Meriton residential or commercial?
Meriton is a hotel or serviced apartments. The City of Melbourne lists its main use as commercial accommodation.
When was Meriton built?
Meriton was completed in 2023.
How many floors does Meriton have?
Meriton has 58 floors above ground.
Does Meriton have hotel or student accommodation?
The City of Melbourne records 298 serviced apartments at Meriton.
Who designed and built Meriton?
Karimbla Properties developed Meriton, Rothelowman designed it and Hickory built it. The building team section has the sources.
How tall is Meriton?
About 188 metres, measured from the City of Melbourne's 3D building model. It's number 26 of 1596 buildings in Melbourne by height.
What public transport is near Meriton?
Southern Cross Station is the nearest train station, about 5 minutes' walk. The nearest tram stop is William St/Bourke St #3, about 2 minutes' walk.
What is the planning zone for Meriton?
The site is in the Capital City Zone - Schedule 1 (CCZ1).
Does Meriton have an owners corporation?
Plan of subdivision TP131993 has 1 lot.
Who bought the 140-146 King Street site?
Meriton bought the 140-146 King Street site in April 2019 for a serviced apartment hotel.
Has any work been done on Meriton recently?
The City of Melbourne has issued 10 building permits for Meriton since 1997. The most recent was in July 2023.
Sources: City of Melbourne building permits (CC BY 4.0); CLUE building information (CC BY 4.0); CLUE business establishments (CC BY 4.0); Development Activity Monitor (CC BY 4.0); Geocoded National Address File (G-NAF) (Open G-NAF EULA (CC BY 4.0 based)). General information from public records, not legal, financial or building advice.