| Construction started | Feb 2011 | First major construction permit issued |
| First occupants | Sep 2013 | First occupancy permit issued |
| Completed | By Jul 2013 | Bourke Junction completed: 16 floors |
Each cost is the estimate on that record. Stages of a project often repeat its full value, so these don't add up to what was spent.
| 17 Dec 2025 | Alterations to the existing NAB Global Operations Command office tenancy in an existing office building | $1.9m |
| 03 Dec 2025 | The proposed project is for Mothers/Wellbeing room at NAB located at L14, 700 Bourke St, Melbourne. | $75k |
| 01 Dec 2025 | Cladding replacement works located at 700 Bourke Street, Docklands. | $848k |
| 01 Aug 2025 | Internal Fit Out - Bakery | $130k |
| 12 Aug 2024 | Lot 3 - Detection alterations to the retail tenancies | $5k |
| 31 July 2023 | Level 3 - NAB ATM Test Lab Fitout | $1.4m |
| 03 July 2023 | P2 - alterations to existing building (mail room smoke alarms & air con unit) | $70k |
| 16 June 2023 | NAB Alterations of Level 10 | $178k |
| 10 May 2023 | NAB Tenancy Alterations Level 2 and 14 | $819k |
| 22 Dec 2022 | Façade Alterations to Outdoor Play Space for Little Stars Childcare | $154k |
| 29 July 2022 | Level 10 - Alterations | $94k |
| 01 Feb 2022 | Level 12 - Proposed alterations to existing office | $116k |
| 28 Jan 2022 | Level 13 - Relocation of BGA & WIP to existing office building. | $2k |
| 03 Dec 2021 | Level 8 - Proposed alterations to existing office | $136k |
| 03 Nov 2021 | Level 13 - Office fitout to part of existing tenancy | $1.0m |
| 31 May 2021 | Level 3 - Alterations to existing office building | $100k |
| 13 Nov 2020 | Level 3 - Proposed new amenities and print area to existing office tenancy | $200k |
| 18 Feb 2020 | Minor Alterations to Existing Façade | $48k |
| 07 Aug 2019 | Level 3 - Proposed alterations to existing office tenancy | $220k |
| 27 May 2019 | Levels 4 to 14 - Proposed alterations to existing office tenancy | $366 |
| 27 May 2019 | Stage 2 – Levels 5 & 10 works | $338k |
| 27 May 2019 | Stage 3 – Levels 6, 11 & 14 works | $449k |
| 27 May 2019 | Stage 4 – Levels 4, 7,12 & 13 works | $916k |
| 10 May 2019 | Level 3 - Proposed installation of access control gates to existing office building | $41 |
| 09 Feb 2018 | Install fire dampers to electrical risers | $21k |
| 29 Apr 2016 | Level 12 - Fit Out | $1.0m |
| 16 June 2015 | Alterations - NAB Level 3, 700 Bourke Street Melbourne New Meeting Room | $144k |
| 08 Nov 2013 | Alterations to Store 804, Mezzanine Level, 700 Bourke Street - New Fire Rated Wall to Store Room | $14k |
| 20 Sept 2013 | New Cafe/Restaurant Tenancy 02002 | $400k |
| 24 July 2013 | Internal fitout and alterations | $2.1m |
| 16 July 2013 | Intemal Tenancy Fitout for NAB | $530k |
| 22 May 2013 | Fit out of ICHI MAKI Shop 1B | $246k |
| 03 May 2013 | Stage 2 - Fitout of Retail Tenancy and all associated works - Shop 3 | $400k |
| 10 Apr 2013 | Alterations-Fitout of retail shop 3 | $400k |
| 04 Mar 2013 | Stage 5: Statutory Signages, Drainage Variation to Eastern Colonnade & Level 14 Landscape Screens - New Building | $224.5m |
| 07 Feb 2013 | Fitout to existing retail complex - Retail 2 | $180k |
| 29 Jan 2013 | Stage 4: Variation to Facade Framing | $224.5m |
| 30 Nov 2012 | Stage 3: New Sky Sign (North Elevation) | $170k |
| 09 Nov 2012 | Stage 2: New Sky Sign (South East Elevation) | $170k |
| 16 Oct 2012 | New building - New sky sign | $170k |
| 19 Sept 2012 | Stage 14: To completion of architectural finishes and fittings including dry wall install - Proposed construction of a mix office & retail development - NAB | $224.5m |
| 10 Sept 2012 | Stage 13: To completion of structural works: Feature Truss - Level 2 concourse; Main Entry Facade; Facades; Bourke Street Entry; Bourke Street Entry Ceiling Support & Precast Lids; South East & South West canopy Design, and; Facde Fissures/Curtain Wall) - Proposed construction of a mix office & retail development - NAB | $224.5m |
| 27 July 2012 | Stage 12: To completion of the fire services and building works relating to the fire control room | $224.5m |
| 19 July 2012 | Stage 11: To completion of the installation and structural details of Level 16 roof and rolling davit support system | $0 |
| 18 May 2012 | Stage 10: To completion of the installation of stormwater drainage | $224.5m |
| 20 Apr 2012 | Stage 9: To completion of the installation of the Electrical, Security, Mechanical, Hydraulic , Lift Services but excluding any fire protection services and the any works to the Fire Control Room. Level 14, Level 15, typical details, block-work and precast panels | $224.5m |
| 20 Mar 2012 | Stage 8: To completion of the structural details relating to Level 14, Level 15, typical details, block-work and precast panels | $224.5m |
| 14 Mar 2012 | Stage 7: To completion of the facade and associated cladding elements from Level 3 up to Level 13 but excluding all fissures and canopies) | $224.5m |
| 11 Nov 2011 | Stage 6: To completion of structural details, including structural slabs, columns, walls and associated structural elements and core walls and slabs up to Level 13 and including building works to all levels up to Level 13 that is within 3m of the title boundaries | $224k |
| 12 July 2011 | Stage 5: Proposed construction of a mix office & retail development | $224.5m |
| 20 May 2011 | Stage 4: Partial demolition to existing foot bridge | $10.8m |
| 08 Apr 2011 | Stage 3: To completion of bulk excavation and structural details, piles and pile caps over the drainage easement E4 and car park easement only being E3 EE while excluding building work to areas within other easements. Proposed construction of a mix office & retail development - NAB | $10.8m |
| 14 Feb 2011 | Stage 2: To completion of bulk excavation and structural details, piles and pile caps to this subject allotment 3 including areas within 3m of the boundary along allotment 2 and existing bridge piers while excluding areas within the Easements. Proposed construction of a mix office & retail development - NAB | $10.8m |
| 31 Jan 2011 | Proposed construction of a mix office & retail development - NAB | $10.8m |
| 24 Apr 2006 | Storage room in carpark. Alterations to an existing building level 1 (part, 1608 only). | $3k |
Is Bourke Junction residential or commercial?
Bourke Junction is a commercial building. The City of Melbourne lists its main use as office.
When was Bourke Junction built?
Bourke Junction was completed in 2013.
How many floors does Bourke Junction have?
Bourke Junction has 16 floors above ground.
What businesses are in Bourke Junction?
The latest council census counted 5 businesses in Bourke Junction, including 90 Secondi, Ichimaki and Mr Grazier.
Is there office or retail space for lease in Bourke Junction?
See the commercial listings on this page, or search this address on realcommercial.com.au and commercialrealestate.com.au.
Who designed and built Bourke Junction?
Cbus Property developed Bourke Junction, Woods Bagot designed it and Brookfield Multiplex built it. The building team section has the sources.
How tall is Bourke Junction?
About 66 metres, measured from the City of Melbourne's 3D building model. It's number 46 of 286 buildings in Docklands by height.
What public transport is near Bourke Junction?
Southern Cross Station is the nearest train station, about 2 minutes' walk. The nearest tram stop is Stadium Precinct - Bourke St/Harbour Esp #D3, about 4 minutes' walk.
What is the planning zone for Bourke Junction?
The site is in the Docklands Zone - Schedule 4 (DZ4).
Does Bourke Junction have an owners corporation?
Plan of subdivision PS623475 has 1 lot.
Who bought Bourke Junction, and for how much?
In 2014, AMP Capital bought the building for $433.5 million.
Has Bourke Junction won an award?
It was highly commended at the 2020 INDE Awards.
Has any work been done on Bourke Junction recently?
The City of Melbourne has issued 41 building permits for Bourke Junction since 2006. The most recent was in December 2025.
Sources: City of Melbourne building permits (CC BY 4.0); CLUE building information (CC BY 4.0); CLUE business establishments (CC BY 4.0); Development Activity Monitor (CC BY 4.0); Geocoded National Address File (G-NAF) (Open G-NAF EULA (CC BY 4.0 based)). General information from public records, not legal, financial or building advice.